Commercial Electrical Refurbishment: How to Estimate What the Drawings Don’t Show
A contractor wins a medical suite refurbishment on a tidy set of drawings. The plans show a spare way in the existing sub-board, reusable cabling above the ceiling and a lighting layout that matches the schedule. On day one the ceiling tiles come off. The sub-board is full, the ceiling space is packed with abandoned cabling, and half the circuits aren’t where the drawings say they are. The tender was priced on what was drawn, not on what was there.
That gap is the core problem in commercial electrical refurbishment. This guide works through the questions an estimator needs to answer before submitting a price on work in an existing building.

What’s actually behind the ceiling?
You rarely know. Drawings for existing buildings are often out of date, partial or based on the original design rather than what was built and later altered. Tenants, previous contractors and maintenance crews have all made changes over the years, and not all of them were recorded.
Start by sorting your scope into what you can see, what you can reasonably infer and what you can’t know until work starts. Visible items, such as fitting types, switchboard layout and accessible cable routes, can be counted and priced with confidence. Inferred items, such as the likely condition of cabling feeding a sub-board, need a stated assumption. Unknowns need to be handled in the tender, not absorbed silently into your margin.
Write your assumptions into the tender. If your price assumes the existing sub-board has spare capacity and that existing cabling can be reused, say so. If the board turns out to be full or the cabling unsuitable, you then have a clear basis to discuss the change with the builder. A pre-tender site inspection checklist is the best way to shrink the unknowns, and we’ll cover that in a separate guide soon.
Ask for anything that helps: as-built drawings, previous maintenance records, switchboard schedules, and access to look above ceilings and inside risers. Where access isn’t offered, record that in your qualifications.
How do you price work in an occupied building?
Working in a live building changes how long everything takes, even if the work is identical to an empty site. Tenants are still trading, treating patients or running meetings. That affects when you can start, how loud or dusty you can be, where you can store materials and how often you must stop and restart.
Estimators often undercount the small, repeated costs of a live site: packing up at the end of each shift, protecting finished areas, moving ladders and tools through occupied space, and coordinating shutdowns with the building manager. Individually they look minor. Across a whole job they can change the labour picture significantly.
Out-of-hours work is the other big question. If outages or noisy tasks must happen at night or on weekends, labour allowances need to reflect that, along with any additional supervision or site access arrangements. Confirm what the builder and the building owner actually expect rather than assuming.
Temporary power is a related issue when you need to keep areas running while others are isolated. That deserves its own detailed treatment, and we’ll cover temporary site power in a separate post.
Any work touching live electrical systems, shutdown procedures or building access is regulated. Confirm requirements for your project with the relevant authority and the builder. For general background on the national building framework, the Australian Building Codes Board is a useful starting point. It doesn’t replace project-specific confirmation.
How do you allow for staging?
Many refurbishments run in stages so part of the building can stay in use. Staging affects your estimate more than most people expect, because the same work gets done in smaller, disconnected pieces.
Each stage means a separate mobilisation, a separate isolation and reinstatement, and often separate testing and handover. Work you’d normally do in one continuous run becomes several partial runs. Materials may need to be ordered in batches or held on site longer, and the same crew may need to return to the same area more than once.
Ask these questions early. How many stages are there, and what sequence are they in? Which services have to stay live through each stage? Does a feed that serves a finished area also serve one still under construction? Where staging creates a “temporary then permanent” condition, such as a circuit rerouted now and finalised later, price both versions of the work.
Check your program assumptions against the builder’s. If the builder’s staging plan changes after award, your labour allowance can change with it, so state the stage assumptions you priced on.
What happens to old equipment?
Removal is not free, and it is easy to under-price. Old switchboards, fittings, cabling and controls need to be disconnected, removed, handled and taken away. Size, weight, access and the number of trips to a skip or loading area all add to the time.
Decide who is responsible for what. Is demolition and disposal in your scope, or does the builder handle it? Is any equipment to be salvaged, relocated or reused? Reuse sounds like a saving, but reused equipment needs checking, testing and sometimes remedial work, and it may not suit its new location.
Older buildings can also contain hazardous materials. This is a regulated area, so confirm requirements for your project with the relevant authority and the builder, and make sure your tender states clearly what is and isn’t included.
New fit-out vs refurbishment: what changes for the estimator
If you’re also pricing new work in a base building, the process is different. Our office and retail fit-out estimating guide covers that side in detail. The table below shows where refurbishment shifts the estimator’s focus.
Area | New fit-out | Refurbishment |
Existing conditions | Largely known, base building documented | Often unknown or poorly documented |
Starting point | Clean, accessible areas | Existing services, congested spaces |
Working environment | Typically unoccupied | Often live, with tenants and the public |
Sequencing | Largely linear | Staged, with repeated isolations |
Old equipment | Minimal | Removal, handling and disposal needed |
Quantities | Measured from new design | Counted on site and verified |
Main risk | Scope and design changes | Unknowns and changed conditions |
How do you price a lighting upgrade and LED retrofit?
Lighting is often the largest and most visible part of a refurbishment, and the part where quantities and assumptions matter most. LED lighting retrofit estimating looks simple on paper, but a retrofit is only as accurate as your understanding of what’s already there.
Existing circuits
Before you assume new LED fittings can go onto existing circuits, check what those circuits actually feed. Older wiring may be in poor condition, mixed with other loads or routed in ways that make reuse impractical. Your price should state clearly whether existing circuits and cabling are being reused or replaced, and what happens if testing shows they can’t be reused.
Existing circuits
Before you assume new LED fittings can go onto existing circuits, check what those circuits actually feed. Older wiring may be in poor condition, mixed with other loads or routed in ways that make reuse impractical. Your price should state clearly whether existing circuits and cabling are being reused or replaced, and what happens if testing shows they can’t be reused.
Fitting counts
Never rely on a drawing alone for fitting counts. Walk the space and count what’s installed, including emergency and exit fittings, specials, and any fittings that look the same but differ in size or mounting. Record the count by area so you can tie your quantities to your price and spot variations later.
Controls
Controls are where retrofit scope often drifts. Will new fittings use the existing switching, or are sensors, dimming or new control wiring part of the job? Where new controls are involved, check whether the building has existing control systems and who is responsible for integration and commissioning. Define it in writing.
Access
Ceiling height, ceiling type and what’s above it affect how long each fitting takes. A suspended grid ceiling with clear access is a very different job from a plasterboard ceiling needing cut-outs, or a high-bay space that needs a lift or scaffold. Allow for access equipment, and for patching or making good where fittings differ in size from those being replaced.
Pricing equipment is the easy part. Time, access and confirmed quantities are what usually cause problems on LED jobs. Any incentive or rebate that might apply to a lighting upgrade is outside what we can advise on here, so check with the relevant authority.
How do you handle contingency on commercial electrical refurbishment?
Because refurbishment carries more unknowns, contingency needs more thought than it does on new work. A flat allowance applied to every job tends to be either too thin for a risky building or needlessly heavy for a simple one.
Tie your contingency to the specific uncertainties you’ve identified: poor documentation, limited access, an old switchboard, unclear existing circuits. A building with several of these warrants a different approach from one with good as-built records. Our guide on how to calculate electrical contingency for construction projects walks through the thinking, and it applies directly to refurbishment work.
Contingency isn’t a substitute for clear qualifications. Where something is excluded or assumed, say so in the tender and use contingency for risks you can’t resolve.
Should you outsource refurbishment pricing?
Refurbishment pricing takes time, and it takes experience of what tends to go wrong in older buildings. Some contractors find tender volumes outstrip their in-house capacity, or that one or two complex refurbishment tenders need careful attention at the same time as live projects.
Outsourcing can help when you want a second set of eyes on assumptions, need quantities checked against site notes, or simply need extra capacity during a busy tender period. If you’re weighing it up, the question is whether an external estimator can give you a more reliable price and clearer qualifications than you’d have time to produce yourself. For Perth contractors, electrical estimating in Perth is one way to bring in extra capacity on refurbishment and other commercial tenders.
Frequently asked questions
What is commercial electrical refurbishment?
Commercial electrical refurbishment is upgrading, altering or replacing electrical systems in an existing commercial building, such as an office, retail tenancy or medical suite. Unlike new work, the estimator has to price around existing conditions, occupied spaces and equipment that is being removed, reused or kept live.
How is electrical refurbishment estimating different from estimating new work?
The main difference is uncertainty. New work is measured from a design, while refurbishment depends on what is actually in the building, much of which can’t be seen until work starts. That makes assumptions, qualifications, staging and site-verified quantities central to the price.
How do you estimate when the existing drawings are out of date?
Treat the drawings as a starting point, not a source of truth. Verify what you can on site, ask for as-built information and maintenance records, and write your assumptions into the tender. Where you can’t verify something, state the assumption and how you’ll deal with changes if it proves wrong.
Is a site visit necessary before pricing a refurbishment?
Wherever access allows, yes. A visit lets you confirm fitting counts, check switchboard condition, see ceiling types and understand how the building operates day to day. If access isn’t provided, record that in your qualifications so the builder knows the price was based on limited information.
How do you price an LED lighting retrofit when fitting counts are uncertain?
Count what’s installed rather than relying on the drawings, and record the numbers by area. If a count can’t be confirmed before tender, state the quantity you’ve assumed and how any difference will be handled. Controls and access need to be priced as well, because they often decide the labour more than the fittings do.
Can an outsourced estimator price a refurbishment without visiting site?
They can, if they have good site notes, photos, switchboard details and a clear picture of access and staging. The quality of the price depends on the quality of that information. The more you can supply from your own inspection, the more reliable the tender will be.
Does a refurbishment need more contingency than new work?
It often needs more careful thinking about contingency rather than a bigger number by default. Link your allowance to the specific unknowns on the job, such as poor documentation, limited access or an old switchboard, and use clear qualifications for anything you can exclude or assume.
Before you submit
Before the tender goes out, go back through the scope as if you were arriving on site on day one. Check that every assumption about existing conditions is written down, including what you’ve assumed about switchboards, cabling, circuits and access. Make sure your allowances for working in a live building and for staging match what the builder expects, not what you’d prefer. Confirm that removal, handling and disposal of old equipment is clearly in or out of scope, and that anything regulated has been referred to the relevant authority and the builder. Check that your LED retrofit counts come from site verification rather than drawings alone, and that controls and access are priced rather than assumed. Finally, read your qualifications as the builder would, and ask whether a changed condition would be clearly covered. Have a refurbishment tender coming up? Talk to the team about how we can help you price it with confidence.
Note: this guide is general and experience-based. Confirm requirements for your project with the relevant authority and the builder.
Conclusion
Commercial electrical refurbishment rewards estimators who treat the building as the real source of information and the drawings as a guide. The jobs that go wrong are rarely the ones with high prices or low prices. They’re the ones where unknown conditions, staging, live-building constraints and old equipment weren’t recognised at tender stage. Price what you can verify, state what you’ve assumed and keep your qualifications clear, and your tender will hold up when the ceiling tiles come off. Do that consistently and refurbishment tenders become a source of steady work for Perth contractors and builders rather than a source of surprises.